The Order of Work in a Kitchen Renovation: A Stage-by-Stage Guide for Metro Vancouver Homes

By Costar Construction

Frequently asked questions

What is the right order of work for a kitchen renovation in Metro Vancouver?

Design and measure first, then get the permits and test for asbestos if the home is older. After that comes demolition, rough-in plumbing, wiring and gas, the rough-in inspections, insulation, drywall, cabinets, countertop templating, finishing work and the final inspections. Each stage depends on the one before it.

Why must plumbing and wiring be inspected before drywall goes up in a kitchen?

The inspector has to see pipes, wires and gas lines while the walls are still open. Coquitlam's inspection guide says work that is covered too early may need to be opened up again for inspection, which costs the owner time and money. Ask your City's inspections office which inspections your permit needs.

Do I need an asbestos test before I tear out my old kitchen in BC?

WorkSafeBC tells homeowners to have the home tested for asbestos before a renovation or demolition starts, and says any asbestos found must be removed or contained before the project begins. Only the areas being renovated need to be surveyed. Since January 1, 2024, asbestos abatement contractors in BC must be licensed.

When are countertops measured in a kitchen renovation?

Countertops are measured after the base cabinets are installed, level and fixed in place. The countertop maker then cuts the stone or other material to fit those real cabinets. If the cabinets move after the measurement, the countertop may no longer fit. Ask your countertop maker when they need the cabinets in place.

How many inspections does a gas range need during a kitchen renovation in BC?

Technical Safety BC asks for an inspection at each stage of construction and again after the work is done. For a homeowner gas permit, at least one inspection must be requested within 180 days of the permit date. In cities that issue their own gas permits, such as Vancouver and Burnaby, the city sets the inspection steps.

How do I book a building inspection in Coquitlam for my kitchen?

Coquitlam books building and plumbing inspections through its online inspections system, which is open 24 hours a day. You need your permit number, and you must book before 4:15 p.m. on the day before the inspection. Check the City's inspections page for the current booking rules.

What does the inspector check at the final inspection of a renovation in Coquitlam?

Coquitlam's guide says the final building inspection needs the final plumbing inspections done first. Safety items such as guardrails, handrails, smoke alarms, carbon monoxide alarms and cooktop clearances must be in place. Ask the City's inspections office for the current checklist before you book the final inspection.

Can the cabinets go in before the rough-in inspection is passed?

Cabinets go on finished walls, so they come after drywall, and drywall comes after the rough-in and insulation inspections. Installing cabinets early can hide pipes and wires the inspector still needs to see. Ask the City's inspections office to confirm which inspections must pass before you order cabinets.