BC Hydro Electrical Service for a Vancouver Multiplex: How the Connection Works, Step by Step

By Costar Construction

Frequently asked questions

Does every new multiplex in Vancouver go through BC Hydro's design connection process?

The City of Vancouver's Multiplex Electrical Process Guide says all multiplexes in Vancouver go through BC Hydro's design connection process. If BC Hydro finds early on that a 200 amp service needs no work on its own equipment, it moves the project to the simpler express connection. BC Hydro's own page also sends a project to design connection when it has four or more meters or needs more than 400 amps.

Who issues the electrical permit for a new multiplex in Vancouver?

The City of Vancouver issues electrical permits inside the city, under authority given by the Province. Technical Safety BC lists Vancouver as one of the local governments that run their own electrical permits. The City's electrical permit page says the applicant must be a licensed electrical contractor with a City of Vancouver or inter-municipal business licence.

Can I pull my own electrical permit for my Vancouver multiplex?

No. The City of Vancouver allows a homeowner permit only for a detached single-family home that the owner lives in, with no secondary suite, no rented part and a service no larger than 200 amps at 120/240 volts. A multiplex does not fit those conditions, so a licensed electrical contractor applies.

Does each home in a Vancouver multiplex get its own BC Hydro meter?

Yes. BC Hydro says it no longer provides one shared master meter to new buildings with several homes, so each new home needs its own meter. Secondary suites are the exception. The City's guide says Vancouver allows up to six meter positions on one service, where the electrical code would otherwise limit a building to four services.

Is overhead or underground BC Hydro service better for a Vancouver multiplex?

BC Hydro prefers overhead service where it is possible. On its small-scale multi-unit housing page it says underground connections can cost up to 10 times more than overhead ones and can take 10 to 18 months to plan and connect. BC Hydro decides which one your lot gets, based on the size of the service, the nearest pole and the site.

How much space should I leave for a BC Hydro transformer on a Vancouver multiplex lot?

BC Hydro asks local governments to make sure site plans show a dedicated space of at least 3.6 metres by 3.6 metres for a low-profile transformer, in case one is needed. It also asks plans to show a 6 metre setback from the building to the nearest transformer on a pole. BC Hydro decides during design whether the transformer is needed.

How do EV chargers affect the electrical service size of a Vancouver multiplex?

Under the Canadian Electrical Code, EV charger loads count at close to full value unless an energy management system controls them. The City's guide shows that a charger on a 20 amp circuit draws at most 16 amps, compared to 32 amps on a 40 amp circuit. In a six-plex with one parking space per home, that saves 96 amps in the calculation.

What does BC Hydro charge to connect a new multiplex in Vancouver?

BC Hydro charges an extension fee, which is your share of the poles, transformers, cable and conduit, minus BC Hydro's contribution. From April 1, 2026 to March 31, 2027, its costs page lists a residential contribution of $2,798 per single-family dwelling. A design deposit may also apply: waived for small projects, $2,000 for medium and $5,000 for large ones. BC Hydro quotes the final amount for each site.