The Builders Lien Holdback in Vancouver: The 10 Percent You Keep Back From Every Payment on a New Home or Multiplex

By Costar Construction

Frequently asked questions

How much holdback do I keep back when I build a house in Vancouver?

Section 4 of BC's Builders Lien Act says the person who pays on a construction contract must keep back 10 percent of the value of the work or material provided, or of the payment made, whichever is greater. This applies whether you pay in stages or in one payment at the end. Your contractor keeps back 10 percent from its own subcontractors in the same way.

When can I release the holdback on my Vancouver custom home?

The holdback period ends 55 days after a certificate of completion is issued for the contract. If no certificate is issued, it ends 55 days after the head contract is completed, abandoned or terminated. Section 8(4) says that if you pay the holdback after the period ends, and no claim of lien was filed and no court action was started in the meantime, the liens tied to that holdback are discharged.

Do I need a separate holdback account for a multiplex build in Vancouver?

Under section 5 of the Builders Lien Act, the owner must open a holdback account at a savings institution for each contract under which a lien may arise, pay the holdback into it, and run it together with the contractor. The rule does not apply to a contract where the total value of work and material is less than $100,000, or where a savings institution lender keeps the holdback for the owner under section 4(4).

Who can file a builders lien on a house in BC?

Section 2 of the Act gives a lien to a contractor, a subcontractor or a worker who does work or supplies material for the project, for the part of the price that is still unpaid. Material suppliers, and architects and engineers whose services count as work under the Act, can claim too. A person who works for or supplies an architect, an engineer or a material supplier has no lien.

How long does a contractor have to file a lien in BC?

Section 20 says a claim of lien must be filed no later than 45 days after a certificate of completion is issued for that contract or subcontract. If there is no certificate, the 45 days run from when the head contract is completed, abandoned or terminated, or from when the project is completed or abandoned. A lien that is not filed in time is extinguished under section 22.

How long does a builders lien stay on my title in BC?

Under section 33, the lien claimant must start a court action and register a certificate of pending litigation within one year of filing the lien, or the lien is extinguished. The owner can shorten this by serving a notice to commence an action, which gives the claimant 21 days. The LTSA says a lien with no legal proceedings after one year can be removed from title with a Form 17.

What happens if I paid my contractor in full and did not keep a holdback?

You can still be liable. Section 34 says lien holders who claim under your contractor may recover up to the greater of what you still owe that contractor and the holdback you were required to keep. So if you paid everything and kept nothing, unpaid subcontractors may still claim up to the 10 percent you should have held. A construction lawyer can tell you where you stand.

Can my BC home building contract say the Builders Lien Act does not apply?

No. Section 42(2) of the Act says an agreement that the Act does not apply, or that its remedies are not available to a person, is void. A clause like that in a home building contract has no effect. Ask your lawyer to read the payment and holdback clauses before you sign.